Aurubis_Richmond (Nov 2022)

The History of Aurubis Richmond

How it all began

Where four years ago there was just fallow land, more than 240 people now work in the largest multimetal recycling plant in the US: Aurubis Richmond LLC in Augusta, Georgia. The story of a true team effort.


Over the course of 2020

The foundation is laid: The rough design and the basic engineering are completed. They form the basis for calling for initial bids.

Aurubis Richmond_Rendering


Summer 2021

Various possible sites had been investigated and evaluated. In September 2021 the decision is made in favor of Augusta in Richmond County, Georgia.

Aurubis_Standort Richmond


September 2021

The company is founded: Aurubis Richmond LLC is legally established and officially registered.

Aurubis_Richmond visitor check in


November 10, 2021

The Supervisory Board approves the construction of a new multimetal recycling plant in Augusta. At the same time, a memorandum of understanding (MoU) is signed between Aurubis and the Georgia Department of Economic Development.

Aurubis_Richmond_Ribbon Cutting (2)

Pat Wilson, Commissioner of the Georgia Department of Economic Development and Roland Harings (former CEO Aurubis AG)


November 26, 2021

Aurubis and SMS sign a contract regarding the planning, delivery and assembly of the main facilities for the new Aurubis plant in the US.

Aurubis Richmond_Rendering_2


June 17, 2022

The groundbreaking takes place with Governor Brian P. Kemp, business partners, and Aurubis representatives. Construction starts on the new plant.

Groundbreaking Aurubis Richmond


November 2022

The blinding layer and the retention pond are nearly finished.

Aurubis_Richmond (Nov 2022)


December 2022

The foundation of the feed mix hall and lab sampling is complete, so construction can now move upward. While construction continues on Phase 1, the Supervisory Board approves the plans for Phase 2, deciding to double capacity.

Aurubis_Richmond (Dec 2022)


Juli 2023

David Schultheis takes over the operative management of the new plant as President & Managing Director.


March 2023

A glimpse into the furnace hall, where an impressive number of cranes are working simultaneously.

Aurubis_Richmond_Richtfest


October/November 2023

The first materials are delivered in a small ceremony. The shredder and smelter furnace start operations as well.

Interior Furnace


February 1, 2024

The team numbers 100 people for the first time; it was just five roughly a year earlier. Over 130 more will behired in the months to come.

Aurubis_Leadership Team


September 20, 2024

Gradual commissioning starts with the ribbon cutting at the new plant.

Aurubis_Richmond_Ribbon Cutting_1_20240920


September 24, 2025

First Melt of Aurubis Richmond: This hot commissioning marks a milestone for Aurubis’ 800 million dollar investment – fulfilling our promise to repurpose and deliver essential American metals, strengthen American supply chains, and drive American industry, American jobs, and American innovation for generations to come.

FIRST MELT Richmond_bunt